A completeness check is not plan review

The code comments start after the set is complete enough to review.

InstaPreView · Published November 12, 2026 · Updated November 12, 2026
Line drawing of a construction drawing sheet with a title block and a revision cloud, titled “A completeness check is not plan review”. InstaPreView by Byts & Bytes.

The most expensive rejection is the one that happens before anyone checks a corridor. Intake sends the set back because a sheet is missing, a seal is missing, or the code edition is blank. That is not a code comment. It is a completeness check. You pay the cycle anyway.

The 2021 IBC describes what the construction documents are for in Chapter 1, Section 107. They have to be enough for the building official to review the work. Section 107.2.7 says the documents include the structural information in Section 1603. Section 107.3.4 names a design professional in responsible charge. Section 107.3.4.1 says deferred items are listed, not omitted in silence. Read the chapter at ICC. The city's intake checklist is stricter than that chapter whenever the city says so. Get the checklist. The required sheets guide is the commercial minimum people forget: a code sheet, architectural plans, accessibility details, and the structural and MEP sheets the scope needs, each with a title block and the required seal.

A practical intake list, before you talk about egress:

  • The project address matches the application, and the adopted edition is named. Find it from the jurisdictions page and confirm it.
  • Every sheet in the index is in the PDF, and the index does not list sheets you did not send.
  • Deferred designs are listed, with the prior-approval story Section 107.3.4.1 requires.
  • Seals and signatures are on the sheets your state requires. A draft stamp is not a seal.
  • The life-safety or code sheet exists as its own sheet, not as a paragraph in an email.

The mistake is treating a completeness return as a comment about means of egress and rewriting Chapter 10 while the missing structural sheet is still missing. Read the letter. If it says "incomplete," send the missing piece. Do not send a new code narrative.

When the set is complete, the code comments start. What reviewers check is that second letter, not the first.

Upload a complete set and run a free scan before intake sees it. The scan is not the completeness check. It is the code pass you can do once the sheets are actually in the file.

This is advisory. It is not a determination by the authority having jurisdiction. Confirm the adopted edition, the intake checklist, and local amendments before you change a drawing.