Who stamps which sheet
Five stamps and no one coordinating them is an incomplete set.
Plan review stalls when every consultant stamped a PDF and nobody is responsible for the set. The 2021 IBC gives that job a name. Section 107.3.4 says that where documents must be prepared by a registered design professional, the building official can require the owner to designate a registered design professional in responsible charge on the permit application. That person reviews and coordinates submittal documents prepared by others, including phased and deferred submittal items, for compatibility with the design of the building. If that person changes, the owner notifies the building official in writing. The section is in Chapter 1.
The section does not say the architect stamps the structural calculations, or that the mechanical engineer stamps the life-safety plan. Which seal may go on which sheet is the state's licensing law. Read that law before you put a seal on work outside the license. What the building code adds is coordination. Someone has to look at the architectural plan, the structural plan, and the mechanical plan and say they describe the same building.
That shows up as ordinary conflicts:
- The architectural code sheet says the building is sprinklered. The fire protection drawings are not in the set and are not listed as a deferred submittal under Section 107.3.4.1. See deferred submittals for the sheet the intake desk expects, and list the deferral in words.
- The door schedule and the floor plan disagree. That is a coordination miss, not a code-theory miss.
- Structural information required by Section 107.2.7, which points at Section 1603, is in a calculation package no one sealed.
Put the name of the design professional in responsible charge on the cover sheet, next to the adopted code edition. The jurisdictions page tells you which edition to print. It does not pick the licensee.
The mistake is a title block full of logos and an empty "responsible charge" line. The reviewer will pick someone and send the comments there. Choose the person before they do.
Before the package goes in, upload the architectural set and run a free scan. Coordination comments are cheaper before the consultants have all sealed.
This is advisory. It is not a determination by the authority having jurisdiction, and it is not a licensing opinion. Confirm the adopted edition, the local amendments, and the state licensing rules before you seal a sheet.