Owners say "it's just a TI" when the activity in the space is changing. Reviewers separate two ideas. An alteration is work on an existing building that keeps the occupancy. A change of occupancy is a change in the occupancy classification, or a change to a higher hazard within the rules of the existing building code. The work can be minor and the occupancy change can still control the review. New paint in a space that stays Group B is not the same project as a retail bay becoming a restaurant.

The International Existing Building Code is the book, once the city has adopted it. The existing buildings guide is the alteration side. The change of occupancy guide is the other side. This post does not cite an IEBC chapter number. Those numbers are easy to take from the wrong edition. Open the adopted IEBC and use its contents page. The model IBC, which still supplies the occupancy definitions the IEBC points at, is at ICC. Chapter 3 of that IBC is what "a different occupancy" means. The occupancy guide summarizes the groups.

How you tell which path you are on, in sentences the code sheet can use:

  • "The suite remains Group B. The work is an alteration. The occupant load changes because the rooms changed." That is still an occupant-load problem. Run Table 1004.5. It is not, by itself, a change of occupancy.
  • "The suite changes from Group M to Group A-2." That is a change of occupancy. Say so. Do not describe it as an alteration and hope the old certificate covers the dining room.
  • "The suite stays Group B and adds ambulatory care." Read the definition before you decide the group did not change. Extra requirements can apply without a new letter. See the clinic scenario, and Section 422 of the adopted IBC.

The tenant improvement checklist assumes you have already answered this. Do that answer in the first paragraph of the code sheet. Confirm the adopted IBC and IEBC editions on the jurisdictions page. They are not always the same cycle.

Upload the code sheet and the plans and run a free scan. If the sheet will not say whether the occupancy changed, the reviewer will decide for you, and you will not like the assumption.

This is advisory. It is not a determination by the authority having jurisdiction. Confirm the adopted edition and local amendments before you change a drawing.