Home › Blog › What a deferred submittal is allowed to leave out
AHJ & Permitting

What a deferred submittal is allowed to leave out

By others is not a deferred submittal.

InstaPreView · Published November 12, 2026 · Updated November 12, 2026
Line drawing of a construction drawing sheet with a title block and a revision cloud, titled “What a deferred submittal is allowed to leave out”. InstaPreView by Byts & Bytes.

"Sprinklers by others" is how a set gets sent back. A deferred submittal is a specific administrative path, and the 2021 IBC writes it in Section 107.3.4.1.

Deferral of any submittal item needs the prior approval of the building official. The registered design professional in responsible charge lists the deferred submittals on the construction documents for that official to review. The deferred documents go back to that design professional first, who reviews them and forwards them with a notation that they conform to the design of the building. The deferred items are not installed until the building official has approved those documents. That is the section. Read it in Chapter 1 of the 2021 IBC.

The section does not hand you a menu. It does not say sprinklers, fire alarm, trusses, and curtain wall are automatically deferred. Some departments allow those. Some want the sprinkler design in the first package. Prior approval means you asked, and someone said yes, before you omitted the sheets. A note you invented in the general notes is not prior approval.

On the cover sheet, list each deferred item in words: what it is, who will submit it, and that it will be reviewed by the design professional in responsible charge before it goes to the building official. Cross-reference the performance the building design depends on. If the architectural life-safety plan takes a sprinkler credit — a 0-hour corridor under Table 1020.2, or a longer dead end under Section 1020.5 — the deferred design has to be the system that credit names, usually an NFPA 13 system under Section 903.3.1.1. You cannot spend the credit and defer the question of which standard you are buying.

The mistake is deferring the thing the rest of the set relies on, and also deferring the list. If it is not on the construction documents, it is not a deferred submittal. It is a missing sheet. The required sheets guide is the intake version of that problem.

Before you submit, upload the set and run a free scan. A missing sprinkler sheet and a deferred sprinkler sheet are not the same comment. The drawings have to say which one you mean.

This is advisory. It is not a determination by the authority having jurisdiction. Confirm the adopted edition and local amendments before you change a drawing.