A phased permit does not finish the review

You may dig. You have not been approved to build the rest.

InstaPreView · Published November 12, 2026 · Updated November 12, 2026
Line drawing of a construction drawing sheet with a title block and a revision cloud, titled “A phased permit does not finish the review”. InstaPreView by Byts & Bytes.

A foundation permit, a grading permit, or a "core and shell only" approval feels like the project is approved. It is approval of the phase someone agreed to review. The rest of the building is still unreviewed. Pouring concrete against a later comment is how projects stop in the ground.

The 2021 IBC does not define a document called a foundation-only permit. It does say, in Section 107.3.4, that the registered design professional in responsible charge coordinates submittal documents prepared by others, including phased and deferred submittal items, for compatibility with the design of the building. Deferred items have their own subsection, 107.3.4.1: prior approval, a list on the construction documents, review by that design professional, and no installation until the building official approves the deferred documents. Both are in Chapter 1.

Whether this city will issue a foundation permit at all is the intake checklist, not Chapter 1. Ask before you promise a construction start. If they will, the submittal usually still has to show that the foundation you want to build belongs to a building that can be permitted: construction type, occupancy, and the structural information Section 107.2.7 points at Section 1603. A footing detail with no code sheet is how the foundation permit gets declined. The structural loads guide is the content of that later package. It does not replace the phase you are asking for now.

Write the limit on the cover sheet in words. "This submittal is for foundations only. Superstructure, egress, and fire protection are a separate submittal and are not approved by this permit." List what is coming later, the way you would list a deferred sprinkler design. Do not let the architectural life-safety plan take credits — rated corridors, travel distance, occupant load — that this phase does not include. Those reviews have not happened. The egress guides are for the phase that contains the exits.

Confirm the edition on the jurisdictions page so the foundation notes cite the code the later phase will also cite. Changing editions between phases is a coordination failure of your own making.

Upload the phase you are actually submitting and run a free scan. Tell the truth about what is not in the file. A scan cannot review sheets you did not upload.

This is advisory. It is not a determination by the authority having jurisdiction. Confirm the adopted edition, the phased-permit rules, and local amendments before you change a drawing.