Home › Blog › The statement of special inspections never made the set
Plan Review

The statement of special inspections never made the set

The calculations can be right and the package can still be incomplete.

InstaPreView · Published November 12, 2026 · Updated November 12, 2026
Line drawing of a construction drawing sheet with a title block and a revision cloud, titled “The statement of special inspections never made the set”. InstaPreView by Byts & Bytes.

Structural calculations in a separate PDF, and no statement of special inspections in the permit set, is a completeness rejection. The reviewer has not disagreed with the shear walls. They cannot see who inspects them.

IBC Chapter 17 is where special inspections live. The registered design professional prepares a statement listing the work that needs a special inspector and whether the inspection is continuous or periodic. The special inspections guide is that requirement in plain language: concrete, structural steel and welding, masonry, soils, and the seismic and wind systems are the usual rows, and the statement belongs in the permit set rather than in a field binder after the permit. This post does not restate the chapter. It is about the set that left the statement out.

The administrative hook is earlier in the book. Section 107.2.7 of the 2021 IBC says the construction documents provide the structural information specified in Section 1603. Read Chapter 1 at ICC. A calculation package no one can find from the sheet index does not satisfy a reviewer who is looking at the architectural PDF only. Put the statement behind a sheet number, name the design professional who prepared it, and make the systems on the statement match the systems on the structural drawings. A statement that lists concrete on a wood building, or omits the steel the details show, fails for a different reason: it does not match the building.

Seismic design category and wind speed change which rows the chapter requires. Those inputs are project-specific. The seismic guide and the wind guide are the places those numbers come from. Do not copy last project's statement.

The mistake is "we will issue the statement if they ask." They will ask, and they will ask at intake, which costs a cycle. The jurisdictions page is where you confirm the IBC edition whose Chapter 17 you are writing to.

Upload the architectural and structural set together and run a free scan before intake. A missing statement is visible without a structural peer review.

This is advisory. It is not a determination by the authority having jurisdiction. Confirm the adopted edition and local amendments before you change a drawing.