Corridor/exit access width is insufficient for the calculated occupant load.
Increase corridor width to a minimum of 44 inches; verify width per occupant load factor (0.2 in/person for level egress).
Jurisdiction note · MI
The InstaPreView code corpus returned edition_trust "provisional" and source_quality "unverified" (corpus updated 2026-06-09). Those are API labels. This page does not treat them as human verification. Mechanical and energy editions are not separate fields in the corpus response, so those corpus cells stay empty unless a future API field exists. The plumbing corpus field is named ipc_edition even when the recorded text is a Uniform Plumbing Code.
| Family | Public sources | Code corpus |
|---|---|---|
| Building |
|
Code corpus MBC 2021 (2021 IBC) |
| Residential | Public sources disagree.
|
Code corpus MRC 2015 |
| Fire |
|
Code corpus 2021 IFC |
| Mechanical |
|
No corpus value for this family. |
| Plumbing |
|
Code corpus MPC 2021 |
| Energy | Public sources disagree.
|
No corpus value for this family. |
| Electrical |
|
Code corpus 2023 NEC |
| Existing building |
|
Code corpus 2021 IEBC |
The commercial accessibility item lists the Michigan Barrier Free Design Law, Public Act 1966 as amended, and the 2017 ICC/ANSI A117.1 standard as referenced from Chapter 11 of the 2021 Michigan Building Code, effective April 9, 2025.
Source: https://troymi.gov/departments/building_inspections/codes_currently_in_effect.php Accessed 2026-11-12. Human verification: not claimed.
The sign-permit page says all new signs must comply with the 2021 Michigan Building Code, Appendix H, as modified by the city. This profile does not quote the modification.
Source: https://troymi.gov/departments/code_enforcement/signs.php Accessed 2026-11-12. Human verification: not claimed.
Name. The City of Troy Building Department says it serves the city through the application of the current Michigan Building Code.
Source: https://troymi.gov/departments/building_inspections/ Accessed 2026-11-12. Human verification: not claimed.
Official page. The codes-in-effect page is https://troymi.gov/departments/building_inspections/codes_currently_in_effect.php.
Source: https://troymi.gov/departments/building_inspections/codes_currently_in_effect.php Accessed 2026-11-12. Human verification: not claimed.
Address. The permit-requirements page directs submittals to the City of Troy Building Department, 500 W. Big Beaver Road, Troy, MI 48084-5285. The site footer lists 500 W. Big Beaver Rd, Troy, Michigan 48084.
Source: https://troymi.gov/departments/building_inspections/permit_requirements.php Accessed 2026-11-12. Human verification: not claimed.
Phone. The Building Department page lists phone 248.524.3344.
Source: https://troymi.gov/departments/building_inspections/ Accessed 2026-11-12. Human verification: not claimed.
Method. The Building Department says it is paperless and only electronic plans are accepted. Permits for electrical, mechanical, plumbing, sewer, and building may be applied for on BS&A Online. Permits that require plan review, and new-construction permits, must be emailed as a PDF to the building department. Commercial building-permit submittals are to be PDF, electronically signed and sealed by an architect, and digitally sized 24 by 36 inches or greater unless the department approves otherwise.
Source: https://troymi.gov/departments/building_inspections/ Accessed 2026-11-12. Human verification: not claimed.
Portal. The online system named for the trade and limited building permits is BS&A Online.
Source: https://troymi.gov/departments/building_inspections/ Accessed 2026-11-12. Human verification: not claimed.
Portal address. The department page says those permits may be applied for at BSAonline.com.
Source: https://troymi.gov/departments/building_inspections/ Accessed 2026-11-12. Human verification: not claimed.
No design-criteria table was filed for Troy, MI.
No official submittal checklist was filed for Troy, MI.
No official ranking of plan-review rejections was found in the sources reviewed for Troy, MI. A generic rejection list is not shown in its place.
InstaPreView's guide to common plan-review comments describes recurring categories on commercial sets: egress and occupant-load errors, accessibility clearances, incomplete documents, energy-code documentation, and a code edition that does not match the one the jurisdiction adopted. That guide is a national pattern. It is not a Troy, MI statistic. Read the guide.
The department email address is image-obfuscated on the codes page, so no email address is filed. The page says residential permit submittals may be submitted through BS&A Online or emailed to the building department.
Source: https://troymi.gov/departments/building_inspections/codes_currently_in_effect.php Accessed 2026-11-12. Human verification: not claimed.
These notes came from the code corpus for Troy, MI. They are not a published rejection ranking from the building department, and they are not human-verified. Corpus trust label: provisional.
Corridor/exit access width is insufficient for the calculated occupant load.
Increase corridor width to a minimum of 44 inches; verify width per occupant load factor (0.2 in/person for level egress).
Building envelope insulation values (R-values / U-factors) or mechanical system efficiencies do not meet 2021 IECC requirements as adopted by Michigan.
Revise construction documents to demonstrate compliance with 2021 IECC prescriptive or performance path; include COMcheck or equivalent compliance report.
Proposed structural alterations or new construction elements are not designed to safely resist all applicable loads (dead, live, snow, wind, etc.) or are not clearly documented with sealed drawings.
Provide structural drawings and calculations sealed by a Michigan-licensed professional engineer, demonstrating compliance with IBC Chapters 16-23 for all structural elements and load conditions specific to Troy, MI.
Occupancy classification not clearly identified or separation requirements not met for mixed occupancies.
Clearly define all occupancy classifications per IBC Chapter 3. Provide fire-resistance-rated construction for mixed occupancies as required by IBC 508.4.
Occupant load calculation incorrect or total egress capacity less than required for calculated occupant load.
Recalculate occupant loads per IBC 1004.1 using appropriate load factors. Ensure minimum required egress width/capacity is provided for all exits based on the calculated occupant load per IBC 1005.3.
Accessible route not provided to all accessible spaces, or required accessible restrooms are non-compliant with dimensional/fixture requirements.
Provide an accessible route from site arrival points to all accessible spaces. Ensure all required accessible restrooms meet dimensional and fixture requirements of IBC Chapter 11 and ICC A117.1.
Automatic sprinkler system required by code but not shown or inadequate coverage/design for the project scope.
Provide an automatic sprinkler system designed per NFPA 13 (or 13R/13D as applicable) where required by IBC 903.2. Submit full sprinkler design documents.
Fire alarm system required but not shown or inadequate components/coverage for the project scope.
Provide a fire alarm system designed per NFPA 72 where required by IBC 907.2, including manual fire alarm boxes, automatic smoke detection, and occupant notification. Submit full fire alarm design documents.
Exit signs or emergency illumination not provided, incorrectly located, or not on an emergency power source.
Install internally or externally illuminated exit signs at all required exit doors and along egress paths. Provide emergency illumination along egress paths with a minimum of 1 footcandle average, connected to an emergency power source.
Energy code compliance documentation (e.g., COMcheck report) is missing or incomplete, or proposed building envelope, mechanical, or lighting systems do not meet minimum efficiency requirements.
Submit complete energy code compliance documentation demonstrating adherence to IECC Chapters C402 (envelope), C403 (mechanical), and C405 (lighting). Ensure specified components meet required efficiencies/R-values for Climate Zone 5.
Insufficient outdoor air ventilation provided for occupied spaces, or required exhaust systems (e.g., restrooms, kitchens) are missing or inadequately sized.
Design mechanical systems to provide minimum outdoor air ventilation rates per IMC Table 403.3. Ensure all required exhaust systems are provided and sized correctly per IMC Chapters 4 and 5.
Required fire-resistance ratings for structural elements or assemblies (e.g., exterior walls, floor assemblies, shaft enclosures) are not met, or openings in rated assemblies are not properly protected (e.g., fire doors, dampers).
Ensure all fire-resistance-rated construction, including walls, floor/ceiling assemblies, shaft enclosures, and protection of openings, complies with IBC Chapter 7 for specified ratings.
Site plan does not demonstrate compliance with local zoning requirements (setbacks, parking, landscaping, stormwater management) or accessible parking is inadequate.
Revise site plan to show compliance with Troy's Zoning Ordinance for setbacks, impervious cover, landscaping, minimum parking (including accessible spaces per IBC 1106), and stormwater management. Provide all required documentation.
Insufficient number of plumbing fixtures provided for the calculated occupant load.
Revise plumbing fixture schedule to provide minimum required water closets, lavatories, and drinking fountains per Michigan Plumbing Code Table 403.1 based on occupancy and occupant load.
Minimum number of plumbing fixtures (water closets, lavatories) not provided based on occupant load and occupancy classification.
Provide the minimum number of water closets, lavatories, and other fixtures as required by IPC Table 403.1 for the calculated occupant load and occupancy type.
The codes-in-effect page says the Michigan codes are the international codes with state amendments, and it lists the 2021 Michigan Building Code as effective April 9, 2025 for commercial work. The InstaPreView code corpus lists "MBC 2021 (2021 IBC)" (corpus trust label: provisional). That label is not human verification.
The City of Troy Building Department says it serves the city through the application of the current Michigan Building Code. The codes-in-effect page is https://troymi.gov/departments/building_inspections/codes_currently_in_effect.php. The permit-requirements page directs submittals to the City of Troy Building Department, 500 W. Big Beaver Road, Troy, MI 48084-5285. The site footer lists 500 W. Big Beaver Rd, Troy, Michigan 48084. The Building Department page lists phone 248.524.3344.
The Building Department says it is paperless and only electronic plans are accepted. Permits for electrical, mechanical, plumbing, sewer, and building may be applied for on BS&A Online. Permits that require plan review, and new-construction permits, must be emailed as a PDF to the building department. Commercial building-permit submittals are to be PDF, electronically signed and sealed by an architect, and digitally sized 24 by 36 inches or greater unless the department approves otherwise. The online system named for the trade and limited building permits is BS&A Online. The department page says those permits may be applied for at BSAonline.com.
The commercial accessibility item lists the Michigan Barrier Free Design Law, Public Act 1966 as amended, and the 2017 ICC/ANSI A117.1 standard as referenced from Chapter 11 of the 2021 Michigan Building Code, effective April 9, 2025. The sign-permit page says all new signs must comply with the 2021 Michigan Building Code, Appendix H, as modified by the city. This profile does not quote the modification.
No. This page is an advisory research note from InstaPreView, a Byts & Bytes product. It is not a permit, not a code interpretation from the authority having jurisdiction, and not a substitute for a licensed design professional. Confirm the edition and the submittal rules with the building department before you rely on them. https://www.instapreview.co/disclaimer
The embedded calculator uses model IBC Table 1004.5 factors. It does not apply a local amendment unless you check that amendment yourself.
Run an advisory pre-review of a Troy, MI plan set. The scan does not issue a permit.
Scan a plan set